[ARCHIVED] SR 57 Freeway/Lambert Interchange Update; Night Work Begin August 28

September 5, 2019 Update


The following is information from Caltrans regarding the tentative schedule and planned work.The City will add updates to this article as they are received from Caltrans. View the latest update from the Caltrans Public Information Office here. To assist in planning your commute, view live traffic conditions using QuickMap and planned lane closures. Keep informed by following Caltrans website and social media platforms: Facebook, Twitter and Instagram

View the project fact sheet here.

Closures for 9/5/19

Work to be done: K-rail installation

  • Thursday (09/05/2019) night from 2200 – 0500 hrs: EB Lambert Rd lanes #1 & #2 from State College to Associate Rd.
  • Thursday (09/05/2019) night from 2200 – 0500 hrs: WB Lambert Rd lanes #1 & #2 from Associate Rd to State College.
  • Thursday (09/05/2019) night from 2200 – 0500 hrs: NB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Thursday (09/05/2019) night from 2200 – 0500 hrs: SB-57 from Tonner Canyon Rd/Brea Canyon to Imperial Hwy/SR-90. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Thursday (09/05/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd off ramp.
  • Thursday (09/05/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd on ramp.
  • Thursday (09/05/2019) night from 2200 – 0500 hrs: SB-57 Lambert Rd off ramp.


CLOSURES (Week of 9/8/19)

Sunday night  9/8/19 (10:00 p.m. - 5:00 a.m.)

  • Sunday (09/08/2019) night from 2200 – 0500 hrs: EB Lambert Rd lanes #1 & #2 from State College to Associate Rd.
  • Sunday (09/08/2019) night from 2200 – 0500 hrs: WB Lambert Rd lanes #1 & #2 from Associate Rd to State College.
  • Sunday (09/08/2019) night from 2200 – 0500 hrs: NB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Sunday (09/08/2019) night from 2200 – 0500 hrs: SB-57 from Tonner Canyon Rd/Brea Canyon to Imperial Hwy/SR-90. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Sunday (09/08/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd off ramp.
  • Sunday (09/08/2019) night from 2200 – 0500 hrs: SB-57 Lambert Rd off ramp.

Monday night 9/9/19 (10:00 p.m. - 5:00 a.m.)

  • Monday (09/09/2019) night from 2200 – 0500 hrs: EB Lambert Rd lanes #1 & #2 from State College to Associate Rd.
  • Monday (09/09/2019) night from 2200 – 0500 hrs: WB Lambert Rd lanes #1 & #2 from Associate Rd to State College.
  • Monday (09/09/2019) night from 2200 – 0500 hrs: NB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Monday (09/09/2019) night from 2200 – 0500 hrs: SB-57 from Tonner Canyon Rd/Brea Canyon to Imperial Hwy/SR-90. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Monday (09/09/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd on ramp.
  • Monday (09/09/2019) night from 2200 – 0500 hrs: SB-57 Lambert Rd off ramp.

Tuesday night 9/10/19 (10:00 p.m. - 5:00 a.m.)

  • Tuesday (09/10/2019) night from 2200 – 0500 hrs: EB Lambert Rd lanes #1 & #2 from State College to Associate Rd.
  • Tuesday (09/10/2019) night from 2200 – 0500 hrs: WB Lambert Rd lanes #1 & #2 from Associate Rd to State College.
  • Tuesday (09/10/2019) night from 2200 – 0500 hrs: NB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Tuesday (09/10/2019) night from 2200 – 0500 hrs: SB-57 from Tonner Canyon Rd/Brea Canyon to Imperial Hwy/SR-90. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Tuesday (09/10/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd on ramp.
  • Tuesday (09/10/2019) night from 2200 – 0500 hrs: SB-57 Lambert Rd off ramp.

Wednesday night 9/11/19 (10:00 p.m. - 5:00 a.m.)

  • Wednesday (09/11/2019) night from 2200 – 0500 hrs: EB Lambert Rd lanes #1 & #2 from State College to Associate Rd.
  • Wednesday (09/11/2019) night from 2200 – 0500 hrs: WB Lambert Rd lanes #1 & #2 from Associate Rd to State College.
  • Wednesday (09/11/2019) night from 2200 – 0500 hrs: NB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Wednesday (09/11/2019) night from 2200 – 0500 hrs: SB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Wednesday (09/11/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd on ramp.
  • Wednesday (09/11/2019) night from 2200 – 0500 hrs: SB-57 Lambert Rd off ramp.

Thursday night 9/12/19 (10:00 p.m. - 5:00 a.m.)

  • Thursday (09/12/2019) night from 2200 – 0500 hrs: EB Lambert Rd lanes #1 & #2 from State College to Associate Rd.
  • Thursday (09/12/2019) night from 2200 – 0500 hrs: WB Lambert Rd lanes #1 & #2 from Associate Rd to State College.
  • Thursday (09/12/2019) night from 2200 – 0500 hrs: NB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Thursday (09/12/2019) night from 2200 – 0500 hrs: SB-57 from Imperial Hwy/SR-90 to Tonner Canyon Rd/Brea Canyon. Alternate lane closure, minimum 2 lanes will be open at all time.
  • Thursday (09/12/2019) night from 2200 – 0500 hrs: NB-57 Lambert Rd on ramp.
  • Thursday (09/12/2019) night from 2200 – 0500 hrs: SB-57 Lambert Rd off ramp.

September 3, 2019 Update

*Please note that in order to safely handle any unforeseen issues and to keep the project on track, it may be necessary to modify the schedule or the work plan.  We will make every effort to update the information as soon as it’s received. 

Project Information

The new Interchange will add capacity and relieve current and future congestion. View the community meeting  PowerPoint Presentation.  Caltrans is the lead agency and is responsible for all aspects of construction management throughout the project, including traffic control and primary public communication.  City staff will meet with Caltrans regularly to get construction updates and will work with the agency on ways to minimize construction disruption and share their public information updates.

The $98 million project is scheduled for completion by December 2021.  Improvements include providing additional capacity, better traffic flow, enhanced safety, reduced congestion and delays. Additionally, the project will enable the future construction of the Northbound Truck Climbing Lane, between Lambert Road and the Orange County and Los Angeles County line. Click here to view a rendering of what the new interchange will look like.

Brea was awarded approximately $75 million from State and Federal funds. The City has also committed about $12 million for the project from its local mitigation funds, and was awarded over $12 million from OCTA Measure M 2 funds, now known as “OC Go” Funds, for property acquisition and construction. All in, approximately 88% of the project funding comes from grants.  City staff will work with Caltrans to minimize construction disruption, manage traffic and support ongoing communication throughout the project.   Keep informed by following Caltrans website and social media platforms: Facebook, Twitter and Instagram.  Additionally, follow the City of Brea official news sources for updates. of new Caltrans information.

View Project Fact Sheet
Facebook Twitter Email

Other News in Brea Top Stories

General Plan Community Open House

Posted on: March 2, 2026

Business Connect Hours

Posted on: March 3, 2026

Small Business Clinic

Posted on: February 25, 2026

Spring Brea Line Now Available

Posted on: January 15, 2026

Pickleball Survey

Posted on: January 13, 2026

Portion of The Tracks Closed Due to Construction

Posted on: August 27, 2025 | Last Modified on: September 10, 2025

Construction Project Status

Posted on: November 12, 2024